SR-519

Partial Interest Acquisitions

Appraisal services, including ongoing consulting, including analysis of the following: airspace lease from BNSF at Royal Brougham Way; right of way acquisition in fee and airspace lease from King County Metro bus base property; right of way acquisition in fee from Mariners property at SE corner of 1st and Atlantic; and easement from Qwest Field Exhibition Center.

Seattle

SR-519 / I-90 / I-5 Interchange

Property areas between 0.6 and 30.8 acres

Max FAR under zoning designations of 2.5-3.0

Acquisition for WSDOT Right of Way

SR-99 – Alaskan Way Viaduct & Seawall Replacement Project

Early Acquisitions and Consulting

Multiple-scenario estimation of real estate value range for all SR-99 project parcels. Scope of work includes project funding estimates; early acquisition appraisals; appraisal services for Colman Curve and Battery Street Tunnel; budget estimate for acquisition of underground utility easements; and ongoing project consulting.

Seattle

Waterfront

200 properties impacted

To assist WSDOT in decisions regarding design alternatives and subsurface utilidor easements

SR-900 – Tibbett’s Creek

Widening and Improvement Project

SR-900 project will widen portions of SR-900, add general-purpose lanes, a bus-only lane southbound and a carpool lane northbound. Initial Project Funding Estimate and Administrative Offer Summary were followed by individual appraisal of 11 properties. Properties impacted include residential and commercial uses.

Issaquah

20 ownerships

Project will entail in-fee and partial acquisitions, as well as TCEs

For Phase II of SR-900 project